Construction Management

Planning and Design - Construction Management - 2017

As a result of the rapid growth of the area, the City of Bowling Green has multiple capital improvement projects on-going throughout the year. These projects include sidewalk and street construction as well as building and park construction.

Street Projects

Smallhouse Widening: Phase 2 (2017-24)
Project to widen Smallhouse Rd. to 3 lanes between Highland Way and Roselawn Way. Construction will include storm sewer, curb and gutter, and an 8 foot wide sidewalk similar to that of Phase 1. Bid was awarded on 7/17/18 to Scotty's Contracting and Stone, LLC. Currently, tree removal, site preparation and waterline relocation is underway. Southbound lane widened is scheduled to be available for traffic December 15, 2018.

Learn More

FY18 Annual Street Resurfacing
Resurfacing of approximately 22.5 miles of city streets and replacement of 50 handicap ramps. Currently waiting for asphalt plant to open this Spring. As a result of the rapid growth of the area, the City of Bowling Green has multiple capital improvement projects on-going throughout the year. These projects include sidewalk and street construction as well as building and park construction.

Learn More

Sidewalk Projects

FY18 New Sidewalk Program (2018-01)
This year's program includes the construction of approximately 4,200 feet of 5 foot wide sidewalk along sections of Park Street, Kenton Street, Magnolia Street North Lee Drive. Project also includes construction of curb and gutter and installation of various drainage structures. Bid process continues.

Learn More

Hogle and Logan Sidewalk (2018-02)
Construction of approximately 2,500 feet of 5 foot wide sidewalk along sections of Hogle Drive and Logan Way. Project also includes construction of curb and gutter and installation of various drainage structures. Project is complete.

Warren Way Sidewalk (2018-03)
Construction of approximately 2,000 feet of 5 foot wide sidewalk along Warren Way between Collegeview Drive and Durbin Drive. Project also includes construction of curb and gutter and installation of various drainage structures. Contract was recently awarded to Scott & Murphy, Inc. and initial construction began in late April with the installation of storm sewer. Construction on concrete sidewalk and curb and gutter started in July. Project is scheduled to be complete by late September.

Drainage Projects

Nutwood St. Drainage (2017-65)
The purpose of this project was to add a storm sewer system along Nutwood Street, beginning near the intersection with Broadway Avenue and connecting with the Glendale storm system at the intersection with 14th Avenue. The project has been completed.

5th Ave. Drainage (2018-04)
This project addressed multiple drainage issues along 5th Ave. between State St. and Center St. by installing a storm sewer system that connects to the Whiskey Run storm sewer near Pioneer Cemetery. The project has been completed.

Paddock Way Drainage (2018-05)
This project addressed multiple drainage issues near Paddock Way and Churchill Court by installing multiple inlets and a storm sewer system that discharges into a nearby basin. This project is substantially complete.

Industrial Dr. Drainage (2018-08)
This project is funded through the City's Stormwater Mitigation program. The purpose of this project is to improve the drainage and pavement condition along Industrial Drive between Dishman Lane and Modern Way. Property acquisition is complete and Atmos Energy has relocated existing gas line in conflict with the proposed storm sewer. Construction bid has been awarded to Charles DeWeese Construction and construction is scheduled to start in August with a scheduled completion of late October.

Robin Road Drainage Improvements (2018-06)
This project consists of new drainage improvements from the Western Green Apartments to the intersection of Robin Road and Clearview Avenue. Expected to be complete by mid-August.

City Facility Projects

Crosswinds Clubhouse Renovations (2018-39)
This project consists of renovations to the existing clubhouse at the Crosswinds Golf Course. Work includes expanding all aspects of the clubhouse including the pro shop, restrooms and concession area. Project is complete.

Police Locker Room and Bathroom Renovations (2018-19)
This project consists of renovation of the Police Station locker rooms and all bathrooms. Project is complete.

Last updated on August 10, 2018.

Is there anything wrong with this page?

Let us know if anything is wrong with this page. However, please don't include any personal or financial information.