Old Morgantown Road Revitalization Project
Once it becomes available, information about progress on the Design Engineer Selection, Final Design, Construction and other phases of the Old Morgantown Road Revitalization Project will be placed here.
Status as of Oct 9, 2008:
The Board of Commissioners approved the changes to the proposed roadway layout and we will begin adverting for proposals for design services for the neighborhood-approved design concept.
Original Proposed Project Schedule
- Oct 7, 2008
(Following BOC concurrence)
Begin Design Consultant Selection - 2 months
- Dec. 1. 2008
Begin Survey/Design - 6 months
- June 1, 2009
Begin Property Acquisition - 8 months
- February 1, 2010
Begin Utility Relocation/Construction - 18 months
- August 1, 2011
Project Complete